<p>In England and Wales, the following offshore wind projects have development consent
and capacities equal or higher than one gigawatt: Dogger Bank Creyke Beck A (1.2GW),
Dogger Bank Creyke Beck B (1.2GW), Dogger Bank Teeside A (1.2GW), Dogger Bank Teeside
B (1.2GW), Hornsea One (1.2GW), Hornsea Two (1.8GW) and Triton Knoll (1.2GW).</p><p>Hornsea
One is currently under construction with target commissioning dates of 31 March 2019,
31 March 2020 and 31 March 2021 for its three phases. Completion dates for the other
projects listed above are not known.</p><p>In Scotland, the Moray Firth offshore wind
project has consent for 1.116GW. The completion date for this project is not known.</p>
|
|