Linked Data API

Show Search Form

Search Results

984402
registered interest false more like this
date remove maximum value filtermore like thismore than 2018-10-09
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Lichfield Trent Valley Station more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, when he plans for work to commence construction to start on the two lifts designed to enable disabled access to all platforms at Lichfield Trent Valley railway station. more like this
tabling member constituency Lichfield more like this
tabling member printed
Michael Fabricant remove filter
uin 177170 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2018-10-17more like thismore than 2018-10-17
answer text <p>Work is due to start on site at the end of November with construction lasting until the end of Spring.</p><p> </p><p>The project will deliver new lifts at platform level at Lichfield Trent Valley to link the West Coast Main Line platforms (platforms 1 and 2) to the Cross City Line platform (platform 3) and provide an accessible route to and between all platforms.</p> more like this
answering member constituency Wealden more like this
answering member printed Ms Nusrat Ghani remove filter
question first answered
less than 2018-10-17T10:56:07.033Zmore like thismore than 2018-10-17T10:56:07.033Z
answering member
4460
label Biography information for Ms Nusrat Ghani more like this
tabling member
280
label Biography information for Michael Fabricant more like this