<p>Guidance in Procurement Policy Note 04/18, published in November 2018 sets out
how payment approaches can be taken into account in the procurement of central Government
contracts (subject to the Public Contracts Regulations 2015) in excess of £5m per
annum.</p><p>This policy note can be viewed at the following link: https://www.gov.uk/government/publications/procurement-policy-note-0418-taking-account-of-a-suppliers-approach-to-payment-in-the-procurement-of-major-contracts.</p><p>