<p>In your constituency of Ceredigion, there are 11 EAS sites, 8 of which have been
designed and have completed the planning approval stage. 4 of the sites have completed
the passive build stage.</p><p>For reference the key stages are:</p><p>1) building
the structure (this is known as ‘passive build’)</p><p>2) connecting the mast to the
network, either by a cable link, microwave link or (on occasions) via a satellite
connection</p><p>3) activating the mast for operational use for the emergency services</p><p>
</p><p>The table attached provides an update on each sites’ progress and shows when
power is forecast to be provided along with a forecast for site activation. After
the award of the contract to connect to the network in Autumn 2021, we anticipate
that a survey of each site will result in activation timelines varying depending on
the work involved, therefore the dates forecast for activation may change accordingly.</p><p>