<p>The Government is working with Ofgem, the Electricity System Operator and network
companies to accelerate network connections. Since the Connections Action Plan[1]
was published in November 2023, over 40GW of projects have been offered earlier grid
connection dates, accelerating up to £40bn of investment. In the coming months we
will decide on further action to ensure only viable projects can retain their connection
agreements. In addition, from next January a new process will prevent projects being
offered a specific connection date until they demonstrate sufficient progress towards
connecting to the grid.</p><p> </p><p>[1] <a href="https://assets.publishing.service.gov.uk/media/655dd873d03a8d001207fe56/connections-action-plan.pdf"