Linked Data API

Show Search Form

Search Results

423610
registered interest false more like this
date less than 2015-10-23more like thismore than 2015-10-23
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading M5: Stroud more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, what progress the Highways Agency has made on noise mitigation measures on the M5 at Upton St. Leonards. more like this
tabling member constituency Stroud more like this
tabling member printed
Neil Carmichael more like this
uin 13170 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2015-11-02more like thismore than 2015-11-02
answer text <p>The main measures to mitigate noise are new road surfacing and noise barriers. Highways England has three resurfacing schemes in their forward programme for this area. The resurfacing will be done after essential repairs to bridge structures have been completed to avoid disruption to users of the M5.</p><br /><p>Later this month works to inspect the condition of the noise fence from junction 11A to Gloucester Painswick bridge which covers the Upton St Leonards section of the M5 motorway will start and opportunities for a temporary noise barrier looked at.</p><br /> more like this
answering member constituency Harrogate and Knaresborough more like this
answering member printed Andrew Jones remove filter
question first answered
less than 2015-11-02T11:37:33.227Zmore like thismore than 2015-11-02T11:37:33.227Z
answering member
3996
label Biography information for Andrew Jones more like this
tabling member
4104
label Biography information for Neil Carmichael remove filter