<p>DCMS officials provided Arqiva with the latest data on notspots, updated by Ofcom
for 2014 with information from the Mobile Network Operators. This shows that coverage
has improved in Fownhope since the inception of the project. The Mobile Infrastructure
Project can intervene in areas where there is no mobile coverage from any operator,
and where the cost of the build of a mast, considered alongside the numbers of premises
that would benefit from the additional coverage, provides value for money. Unfortunately
this is no longer the case for the proposed mast location in Fownhope, and Arqiva
made a recommendation to officials to not proceed.</p><p> </p><p> </p><p> </p>
|
|