<p>Network Rail has been instructed to design an extension of electrification infrastructure
from Kettering to Market Harborough station, as part of the Midland Main Line enhancements
programme.</p><p> </p><p>The Overhead Line Equipment (OLE) extension to Market Harborough
will enable a new connection to a power supply at Braybrooke. At Outline Business
Case stage in March 2018 this was determined to be the best value for money option
for making the power supply connection. In line with normal practice, this will be
tested again when the overall Midland Main Line programme Key Output 1a, of which
Market Harborough electrification is a constituent part, is assessed at Full Business
Case stage.</p><p> </p>
|
|