hansard heading Grenfell Tower: Fires more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 3 November 2017 to Question 110635, on Grenfell Tower: fires, what discussions he has had with the Metropolitan Police on the timescale for (a) concluding the investigation and (b) publishing the report. more like this
tabling member constituency Hammersmith more like this
tabling member printed
Andy Slaughter more like this
uin 133339 more like this
answer
answer
is ministerial correction false more like this
date of answer remove filter
answer text <p>Speaking at the Grenfell Tower Inquiry’s procedural hearing on 21 March, the Metropolitan Police Service’s legal representative remarked that the forensic and evidential picture about the cause and spread of the Grenfell Tower fire was not going to be complete until autumn 2018.</p> more like this
answering member constituency Esher and Walton remove filter
answering member printed Dominic Raab more like this
question first answered
less than 2018-03-26T13:00:47.803Zmore like thismore than 2018-03-26T13:00:47.803Z