1698345
registered interest false more like this
date less than 2024-03-25more like thisremove minimum value filter
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Mill Hill Broadway Station: Access more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, with reference to the Written Statement of 4 April 2019 on Access for All, HCWS1484, for what reason work to provide step-free access at Mill Hill Broadway has not yet started. more like this
tabling member constituency Hendon remove filter
tabling member printed
Dr Matthew Offord more like this
uin 20273 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2024-04-18more like thismore than 2024-04-18
answer text <p>There are many technical issues to overcome at this station, given it is located on the Midland Main Line and adjacent to the M1 motorway, all of which are currently under consideration.</p><p><strong> </strong></p><p><strong> </strong></p> more like this
answering member constituency Bexhill and Battle remove filter
answering member printed Huw Merriman more like this
question first answered
less than 2024-04-18T13:04:55.023Zmore like thismore than 2024-04-18T13:04:55.023Z
answering member
4442
label Biography information for Huw Merriman more like this
tabling member
4006
label Biography information for Dr Matthew Offord more like this
1698346
registered interest false more like this
date less than 2024-03-25more like thisremove minimum value filter
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Mill Hill Broadway Station: Access more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, with reference to the Written Statement of 4 April 2019 on Access for All, HCWS1484, what recent estimate he has made of when work to provide step-free access at Mill Hill Broadway will be started. more like this
tabling member constituency Hendon remove filter
tabling member printed
Dr Matthew Offord more like this
uin 20274 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2024-04-18more like thismore than 2024-04-18
answer text <p>The Access for All project at Mill Hill Broadway station is at the outline design stage. Network Rail are in the process of reviewing and challenging the cost estimate provided by the contractor.</p><p> </p> more like this
answering member constituency Bexhill and Battle remove filter
answering member printed Huw Merriman more like this
question first answered
less than 2024-04-18T12:55:00.973Zmore like thismore than 2024-04-18T12:55:00.973Z
answering member
4442
label Biography information for Huw Merriman more like this
tabling member
4006
label Biography information for Dr Matthew Offord more like this
1698347
registered interest false more like this
date less than 2024-03-25more like thisremove minimum value filter
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Railway Stations: Access more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, with reference to the Written Statement of 4 April 2019 on Access for All, HCWS1484, how many and what proportion of the projects awarded funding through the Access for All programme (a) have been and (b) are yet to be completed. more like this
tabling member constituency Hendon remove filter
tabling member printed
Dr Matthew Offord more like this
uin 20275 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2024-04-19more like thismore than 2024-04-19
answer text <p>Approximately 45% of the current Access for All programme has entered into passenger service, with approximately 55% not yet complete although the majority of these are in construction.</p><p> </p> more like this
answering member constituency Bexhill and Battle remove filter
answering member printed Huw Merriman more like this
question first answered
less than 2024-04-19T07:47:04.883Zmore like thismore than 2024-04-19T07:47:04.883Z
answering member
4442
label Biography information for Huw Merriman more like this
tabling member
4006
label Biography information for Dr Matthew Offord more like this