<p><strong></strong></p><p>The Mobile Infrastructure Project is being rolled out in
Northern Ireland up to the end of March 2016.</p><br /><p>There are currently 7 masts
in build phase. These are located in:</p><p>• Derry and Strabane District</p><p>•
Fermanagh and Omagh (2 sites)</p><p>• Lisburn and Castlereagh</p><p>• Mid Ulster (3
sites)</p><br /><p>Planning permission was received for 4 sites. These sites are located
in:</p><p>• Mid Ulster (3 sites)</p><p>• Newry, Mourne and Down</p><br /><p>Planning
applications were submitted but decisions awaiting for 5 other sites. These are located
in:</p><p>• Armagh, Banbridge and Craigavon</p><p>• Derry and Strabane District</p><p>•
Fermanagh and Omagh (2 sites)</p><p>• Mid Ulster</p>
|