Linked Data API

Show Search Form

Search Results

754586
registered interest false more like this
date less than 2017-07-20more like thismore than 2017-07-20
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading RAF Northolt: Aviation more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Defence, what the cost of the runway re-surfacing works at RAF Northolt will be. more like this
tabling member constituency Harrow West more like this
tabling member printed
Gareth Thomas remove filter
uin 6534 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-09-06more like thismore than 2017-09-06
answer text <p>The cost for the whole RAF Northolt project is £35 - £45 million. The cost includes all work on site and is directly comparable to similar commercial projects. The cost of the runway re-surfacing cannot be separated out.</p> more like this
answering member constituency Bournemouth East remove filter
answering member printed Mr Tobias Ellwood more like this
grouped question UIN 6535 more like this
question first answered
less than 2017-09-06T15:57:10.32Zmore like thismore than 2017-09-06T15:57:10.32Z
answering member
1487
label Biography information for Mr Tobias Ellwood more like this
tabling member
177
label Biography information for Gareth Thomas more like this
754591
registered interest false more like this
date less than 2017-07-20more like thismore than 2017-07-20
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading RAF Northolt: Aviation more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Defence, for what reasons the runway re-surfacing works at RAF Northolt are to cost up to £45 million when similar re-surfacing works at commercial airports have had significantly lower costs. more like this
tabling member constituency Harrow West more like this
tabling member printed
Gareth Thomas remove filter
uin 6535 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-09-06more like thismore than 2017-09-06
answer text <p>The cost for the whole RAF Northolt project is £35 - £45 million. The cost includes all work on site and is directly comparable to similar commercial projects. The cost of the runway re-surfacing cannot be separated out.</p> more like this
answering member constituency Bournemouth East remove filter
answering member printed Mr Tobias Ellwood more like this
grouped question UIN 6534 more like this
question first answered
less than 2017-09-06T15:57:10.387Zmore like thismore than 2017-09-06T15:57:10.387Z
answering member
1487
label Biography information for Mr Tobias Ellwood more like this
tabling member
177
label Biography information for Gareth Thomas more like this