question text To ask the Secretary of State for Transport, whether he has had discussions with HS2 Ltd on the use of target cost contracts instead of geotechnical baseline reports; and what assessment he has made of the potential effect on the level of compensation arising from damage to vulnerable buildings along the High Speed Two construction route of excluding the use of those reports. more like this
tabling member constituency Hampstead and Kilburn more like this
tabling member printed
Tulip Siddiq more like this
uin 196827 more like this
answer
answer
is ministerial correction false more like this
date of answer remove filter
answer text <p>The actual geotechnical parameters from HS2 project ground investigations have been and are being used for the assessment of buildings impacted by the works. Geotechnical baseline reports (GBR) are not precluded by target cost contracts however their use is not considered relevant for the assessment of the impact of potential ground movement on buildings or associated compensation.</p> more like this
answering member constituency Wealden more like this
answering member printed Ms Nusrat Ghani more like this
question first answered
less than 2018-12-03T14:53:21.353Zmore like thismore than 2018-12-03T14:53:21.353Z
answering member
4460
label Biography information for Ms Nusrat Ghani more like this
tabling member
4518
label Biography information for Tulip Siddiq more like this