1681124
registered interest false more like this
date less than 2024-01-10more like thismore than 2024-01-10
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport remove filter
hansard heading Hammersmith Bridge: Repairs and Maintenance more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, whether his Department has made an estimate of when Hammersmith Bridge will be reopened to (a) buses, (b) emergency service vehicles and (c) cars. more like this
tabling member constituency Richmond Park more like this
tabling member printed
Sarah Olney more like this
uin 9031 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2024-01-16more like thismore than 2024-01-16
answer text <p>Hammersmith Bridge is expected to be reopened to all forms of motor vehicle following the completion of the second, ‘Strengthening’ stage of works. The London Borough of Hammersmith and Fulham – as the owner and lead for the Hammersmith Bridge project – has produced a business case for the second stage of works, which is currently being considered by the Government. The schedule for the ‘Strengthening’ works is under development.</p><p> </p> more like this
answering member constituency Bexhill and Battle more like this
answering member printed Huw Merriman more like this
question first answered
less than 2024-01-16T10:05:23.847Zmore like thismore than 2024-01-16T10:05:23.847Z
answering member
4442
label Biography information for Huw Merriman more like this
tabling member
4591
label Biography information for Sarah Olney remove filter