answer text |
<p>As is the case with all of our Local Full Fibre Network (LFFN) projects, DCMS has
assigned a Project Director to work with the Local Body project teams. The project
will firstly be assured through the formal BDUK assurance process via a series of
gateway review points. As the project progresses into delivery, this will be reviewed
through weekly updates into the LFFN Programme Office on delivery progress, finances/grant
claims, change management, and risks/issues - in line with the North Wales project
consortia project plan. We use an online Portfolio Management system called Cora PPM
to facilitate this. All of this is in line with our overall DCMS Governance model
and includes reporting up from the LFFN Programme Board to the DCMS portfolio board
which is chaired by our Permanent Secretary. Additionally LFFN is categorised as a
Government Major Projects Portfolio (GMPP) Programme and is therefore monitored by
the Infrastructure and Projects Authority (IPA).</p>
|
|