Linked Data API

Show Search Form

Search Results

1047090
star this property registered interest false more like this
star this property date less than 2019-01-23more like thismore than 2019-01-23
star this property answering body
Wales Office more like this
star this property answering dept id 28 more like this
unstar this property answering dept short name Wales more like this
star this property answering dept sort name Wales more like this
star this property hansard heading Renewable Energy: Wales more like this
star this property house id 1 more like this
star this property legislature
25259
star this property pref label House of Commons more like this
star this property question text To ask the Secretary of State for Wales, what estimate he has made of the total value of UK Government funded renewable energy projects that have been cancelled in Wales in the last three years. remove filter
star this property tabling member constituency Cardiff Central remove filter
star this property tabling member printed
Jo Stevens more like this
star this property uin 211801 more like this
star this property answer
answer
star this property is ministerial correction false more like this
star this property date of answer less than 2019-01-28more like thismore than 2019-01-28
star this property answer text <p>On 19 October 2018, the Low Carbon Contracts Company (LCCC) announced that it had terminated the contract for difference awarded to Station Yard CFD 1 during the second Contracts for Difference (CfD) allocation round in 2017. Station Yard is a 0.05MW Advanced Conversion Technology with Combined Heat and Power project located in Llangadog, Carmarthenshire. The project’s contract was terminated because it failed to make sufficient progress towards meeting its milestone requirement to demonstrate a commitment within one year of signing a CfD to deliver the project. It is estimated that had Station Yard been commissioned it would have received support of less than £70,000 (in 2017/18 prices) for electricity generated over the 15-year period of its contract.</p><p> </p><p>A CfD is a private law contract between a generator and the LCCC, a government-owned company. CfDs are managed independently by the LCCC and decisions as to whether a generator has met its milestone requirement are for the LCCC. The milestone requirement is a contractual requirement. Failure to meet this requirement may result in a CfD being terminated.</p><p> </p><p>The Government is not aware of any other renewable energy projects in receipt of funding from CfDs or other UK Government schemes that have been cancelled in Wales during this time period.</p><p> </p><p> </p><p> </p><p> </p>
unstar this property answering member constituency Vale of Glamorgan more like this
star this property answering member printed Alun Cairns remove filter
star this property question first answered
less than 2019-01-28T15:45:39.197Zmore like thismore than 2019-01-28T15:45:39.197Z
star this property answering member
4086
star this property label Biography information for Alun Cairns more like this
star this property tabling member
4425
unstar this property label Biography information for Jo Stevens more like this