answer text |
<p>Ofgem is responsible for awarding regulatory approval to electricity interconnector
projects in Great Britain. There are two main routes to regulatory approval, through
the awarding of a cap and floor regime, or a merchant route. Including both routes,
Ofgem has given approval to the following projects:</p><ul><li>IFA 2000MW (GB - France)</li><li>Moyle
500MW (GB - Northern Ireland)</li><li>BritNed 1000MW (GB - Netherlands)</li><li>East-West
500MW (GB - Republic of Ireland)</li><li>Nemo Link 1000MW (GB - Belgium)</li><li>IFA2
1000MW (GB - France)</li><li>North Sea Link (NSL) 1400MW (GB - Norway)</li><li>ElecLink
1000MW (GB-France)</li><li>Viking Link 1400MW (GB - Denmark)</li><li>Greenlink 500MW
(GB - Republic of Ireland)</li><li>GridLink 1250MW (GB - France)</li><li>FAB 1250MW
(GB - France)</li><li>NeuConnect 1400MW (GB-Germany)</li></ul><p> </p><p>Ofgem is
assessing a selection of projects that applied for regulatory approval through the
third cap and floor application window. These results are interim and are being consulted
upon. The final decision will be made in summer 2024 by Ofgem. The projects that are
awaiting final regulatory decisions are:</p><ul><li>Aminth 1400MW (GB - Denmark)</li><li>Cronos
1400MW (GB - Belgium)</li><li>NU-Link 1200MW (GB - the Netherlands)</li><li>LirIC
700MW (GB - Northern Ireland)</li><li>MaresConnect 750MW (GB-Republic of Ireland)</li><li>Aquind
2000MW (GB - France)</li><li>Nautilus 1400MW (GB - Belgium)</li><li>Tarchon 1400MW
(GB - Germany)</li><li>Lion Link 1800MW (GB-the Netherlands)</li></ul>
|
|