hansard heading AWE Burghfield more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Defence, what his timeframe is for completing the construction of MENSA. more like this
tabling member constituency Wentworth and Dearne more like this
tabling member printed
John Healey more like this
uin 43 remove filter
answer
answer
is ministerial correction false more like this
date of answer less than 2022-05-18more like thismore than 2022-05-18
answer text <p>The original and current approved costs and the current in-service dates for Project Mensa and Project Pegasus are as follows:</p><p> </p><table><tbody><tr><td><p>Project</p></td><td><p>Original Cost Approved in 2011</p></td><td><p>Current Approved Cost</p></td><td><p>Approved In-service Date</p></td></tr><tr><td><p>MENSA</p></td><td><p>£734 million</p></td><td><p>£1996 million</p></td><td><p>2024</p></td></tr><tr><td><p>PEGASUS</p></td><td><p>£634 million</p></td><td><p>£634 million</p></td><td><p>Material Handling Store - 2025 Manufacture Capability – 2030</p></td></tr></tbody></table><p> </p><p> </p> more like this
answering member constituency Horsham more like this
answering member printed Jeremy Quin more like this
grouped question UIN
44 more like this
45 more like this
question first answered
less than 2022-05-18T15:27:11.5Zmore like thismore than 2022-05-18T15:27:11.5Z
answering member
4507
label Biography information for Sir Jeremy Quin more like this
tabling member
400
label Biography information for John Healey more like this