hansard heading Railway Stations: Finance more like this
house id 1 more like this
legislature
25259
question text To ask the Secretary of State for Transport, what assessment he has made of the effect of the fixed cost to local authorities for submitting bids to the New Station Fund on the number of bids being made. more like this
tabling member constituency York Outer remove filter
tabling member printed
Julian Sturdy more like this
uin 31569 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2016-03-29more like thismore than 2016-03-29
answer text <p>In order to qualify to bid for funding from the first or current round of the New Stations Fund, proposals need to be sufficiently developed in accordance with Network Rail’s Governance for Railway Investment Projects (‘GRIP’) process, achieving approval in principle at GRIP 3 stage – option selection. We do not believe that the additional cost of submitting a bid would be so burdensome as to deter a bid being made.</p><p> </p> more like this
answering member constituency Harrogate and Knaresborough more like this
answering member printed Andrew Jones more like this
question first answered
less than 2016-03-29T14:05:21.137Zmore like thismore than 2016-03-29T14:05:21.137Z
answering member
3996
label Biography information for Andrew Jones more like this
tabling member
4079
label Biography information for Julian Sturdy more like this