question text To ask the Secretary of State for Defence, what is the planned initial operating capability date for the next generation of Skynet communications satellites. more like this
tabling member constituency Rayleigh and Wickford more like this
tabling member printed
Mr Mark Francois more like this
uin 194166 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2023-07-21more like thismore than 2023-07-21
answer text <p>The contracted date for initial operating capability of SKYNET 6A is January 2026, which is defined as having seven of the ultra-high frequency channels available for operational use by Ministry of Defence and allied personnel.</p><p>Competitions to procure subsequent geostationary satellites are underway, with the most likely initial operating capability dates being 2028 for the first satellite, 2030 for the second, 2032 for the third and 2036 for the fourth.</p> more like this
answering member constituency South Suffolk more like this
answering member printed James Cartlidge remove filter
question first answered
less than 2023-07-21T09:09:40.61Zmore like thismore than 2023-07-21T09:09:40.61Z
answering member
4519
label Biography information for James Cartlidge more like this
tabling member
1444
label Biography information for Mr Mark Francois more like this