1285133
registered interest false more like this
date less than 2021-02-09more like thismore than 2021-02-09
answering body
Department for Transport remove filter
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading M11: Construction remove filter
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, how much funding from the public purse has been allocated to the construction of the new Junction 7a on the M11. more like this
tabling member constituency Harlow more like this
tabling member printed
Robert Halfon more like this
uin 151672 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2021-02-16more like thismore than 2021-02-16
answer text <p>Total project costs for the Junction 7a M11 scheme, including construction and widening of local link roads, is estimated to be around £81 million with an agreed funding contribution from Highways England of £41.7 million, which was provided to Essex County Council. Additionally, through the Department’s Large Local Majors programme, the scheme received £1.5 million of early development funding in 2017. The remainder of the project costs are being funded by Essex County Council and partners.</p> more like this
answering member constituency Redditch more like this
answering member printed Rachel Maclean more like this
question first answered
less than 2021-02-16T11:53:58.41Zmore like thismore than 2021-02-16T11:53:58.41Z
answering member
4668
label Biography information for Rachel Maclean more like this
tabling member
3985
label Biography information for Robert Halfon remove filter