question text To ask the Secretary of State for Transport, what progress his Department has made on the capacity improvement scheme planned for the Hope Valley Line; and what recent discussions he has had with Network Rail to ensure that work is completed as quickly as possible. more like this
tabling member constituency Barnsley Central more like this
tabling member printed
Dan Jarvis more like this
uin 291416 more like this
answer
answer
is ministerial correction false more like this
date of answer remove maximum value filtermore like thismore than 2019-10-02
answer text <p>Network Rail have completed the single option design for the railway infrastructure scheme proposed in the Hope Valley and are working on plans to progress the work to the next stage ‘Decision to Deliver’. Network Rail have developed a procurement plan to deliver the scheme, and <em>expect to contact potential </em>suppliers shortly<em>.</em> They will be working with the train operators to assess the best way to deliver this scheme during control period 6 (2019-2024) with the least disruption to passengers.</p> more like this
answering member constituency Daventry more like this
answering member printed Chris Heaton-Harris more like this
question first answered
less than 2019-10-02T16:11:13.343Zmore like thismore than 2019-10-02T16:11:13.343Z
answering member
3977
label Biography information for Chris Heaton-Harris more like this
tabling member
4243
label Biography information for Dan Jarvis more like this