528205
registered interest false more like this
date less than 2016-06-20more like thismore than 2016-06-20
answering body
Department for Transport remove filter
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading High Speed 2 Line more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty’s Government when they expect the Cabinet Secretary to conclude the HS2 cost review; and whether they will place a copy of his conclusions in the Library of the House. more like this
tabling member printed
Lord Truscott more like this
uin HL771 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2016-07-04more like thismore than 2016-07-04
answer text <p>As is normal for large projects, the Cabinet Office’s Infrastructure and Projects Authority (IPA) is conducting assurance of the HS2 programme as it proceeds into its delivery phase. It is standard practice for this to include a small cross Government team, and not unusual for the Cabinet Secretary to take an interest on projects of this scale. ‎</p><p> </p><p>Headlines from the IPA's work on Phase 2 of High Speed 2 has now been reported in a NAO report on the HS2 project, published on 28 June. The work informs future cost estimates for HS2, as these are developed.</p> more like this
answering member printed Lord Ahmad of Wimbledon more like this
question first answered
less than 2016-07-04T13:14:20.15Zmore like thismore than 2016-07-04T13:14:20.15Z
answering member
4210
label Biography information for Lord Ahmad of Wimbledon more like this
tabling member
3682
label Biography information for Lord Truscott more like this