hansard heading High Speed 2 Line more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty's Government what is the approximate quantity of steel rail required for the HS2 project. more like this
tabling member printed
Lord Trefgarne remove filter
uin HL15945 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2019-06-04more like thismore than 2019-06-04
answer text <p>As stated in the Working Draft Environmental Statement (p.136), the approximate total of steel required for the HS2 project is 1.94 million metric tonnes.</p><p> </p><p>The procurements for contracts that will involve the purchase of steel have not yet concluded so no contract awards have been made. However, HS2 Ltd has already engaged with thousands of British businesses, to aid them in winning work on HS2. So far 98% of contracts for HS2, awarded directly and through the supply chain, have been won by British companies, with many more opportunities to come in the future. HS2 Ltd has let around £10bn worth of contracts and by the end of next year that will be around £20bn.</p> more like this
answering member printed Baroness Vere of Norbiton more like this
question first answered
less than 2019-06-04T13:39:11.19Zmore like thismore than 2019-06-04T13:39:11.19Z
answering member
4580
label Biography information for Baroness Vere of Norbiton more like this
tabling member
1813
label Biography information for Lord Trefgarne more like this