hansard heading Crewe Station more like this
house id 2 more like this
legislature
25277
pref label House of Lords remove filter
question text To ask His Majesty's Government what is the reason for removing the roof at Crewe Station and when they expect it to be reroofed, if at all. more like this
tabling member printed
Lord Blencathra more like this
uin HL4323 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2024-05-16more like thismore than 2024-05-16
answer text <p>The canopies and main trainshed roof have limited asset remaining life and Network Rail expects replacement work to be complete by 2029. The Government has provided £44.1 billion to Network Rail for renewals work during this Control Period (2024-29) which will be used to fund the work.</p> more like this
answering member printed Lord Davies of Gower more like this
question first answered
remove filter
answering member
4499
label Biography information for Lord Davies of Gower more like this
tabling member
497
label Biography information for Lord Blencathra more like this