<p>The Church Commissioners are involved in the development of Paston Reserve in Peterborough.
Within the development there is provision for a site and financial contributions towards
the delivery of a primary school site as outlined within the agreed Section 106 legal
agreement that accompanied the planning permission, and that was varied by agreement
with the Council in 2010. The Section 106 agreement provides that the primary school
site must be delivered prior to any house occupation on the third phase of development
on the site and also outlines the trigger points at which the financial contributions
for the school will be provided.</p><p /> <p>Based on these legal requirements, the
land for the primary school site at Paston Reserve has not been provided yet, because
the site has not progressed to a third phase of development. The first phase on the
site is still under construction, and as outlined in our response to the hon. Gentleman’s
question [3389] answered on the 29 June 2015, the second phase of development is likely
to commence at some point in 2016. The development remains in accordance with the
legal provisions of the Section 106 agreed with Peterborough Council.</p><br />
|
|