<p>The HS2 works to Granby Terrace bridge, which include the partial demolition of
the existing bridge and the construction of a new extension over the HS2 alignment,
was scope originally allocated to the Early Works Contractor Costain Skanska JV (CSJV).
To enable the efficient delivery of the HS2 works, HS2 Ltd reviews which of its Contractors
is best placed to deliver specific scope items where there is an opportunity to deliver
cost savings, schedule benefits or reduce interface risks. Following careful consideration,
HS2 Ltd concluded that the Main Works Civils Contractor (Skanska Costain Strabag JV)
is better placed to undertake the works because of the benefits to the overall HS2
programme and therefore decided to transfer the scope.</p><p> </p>
|
|