question text To ask Her Majesty's Government what assessment they have made of the progress of the programme to ensure that the Navy's fleet of destroyers are fully fit for operations. more like this
tabling member printed
Lord Empey more like this
uin HL16739 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2019-07-04more like thismore than 2019-07-04
answer text <p>The first Type 45 destroyer is due to undergo Power Improvement Project upgrades in 2020 and will be returning to sea trials in 2021. Our £160 million investment in the Power Improvement Project will provide increases in both power generation and reliability for the rest of the Type 45 destroyers' service life. It is planned that all six ships should have completed their upgrade during the mid-2020s.</p><p>Like all Royal Navy ships, the Type 45 destroyers rotate through planned operating cycles involving maintenance, training, deployment, leave and capability upgrades. This results in individual ships being at various levels of readiness. The Type 45 Destroyers continue to be deployed on operations and contribute to the defence of the UK and our international partners.</p> more like this
answering member printed Earl Howe more like this
question first answered
less than 2019-07-04T15:34:47.793Zmore like thismore than 2019-07-04T15:34:47.793Z
answering member
2000
label Biography information for Earl Howe more like this
tabling member
4216
label Biography information for Lord Empey more like this