answer text |
<p>The table below provides details for the projects which have opened to traffic
since 2015/16, the length of the scheme in miles, and the latest approved outturn
cost for each. The data shows that over 200 lane miles have been added to the motorway
network through these schemes since 2015/16.</p><table><tbody><tr><td><p>Open to Traffic</p></td><td><p>Scheme</p></td><td><p>Scheme
length</p></td><td><p>Outturn cost (£m)</p></td></tr><tr><td><p>2015/16</p></td><td><p>M1
Junctions 28-31</p></td><td><p>18.9</p></td><td><p>206.70</p></td></tr><tr><td><p>2015/16</p></td><td><p>M6
Junctions 10a-13</p></td><td><p>9.6</p></td><td><p>102.20</p></td></tr><tr><td><p>2016/17</p></td><td><p>M1
Junctions 32-35A</p></td><td><p>9.1</p></td><td><p>125.50</p></td></tr><tr><td><p>2015/16</p></td><td><p>M1
Junctions 39-42</p></td><td><p>6.7</p></td><td><p>127.70</p></td></tr><tr><td><p>2017/18</p></td><td><p>M3
Junctions 2-4A</p></td><td><p>13.4</p></td><td><p>274.20</p></td></tr><tr><td><p>2017/18</p></td><td><p>M1
Junctions 19-16</p></td><td><p>14.4</p></td><td><p>194.30</p></td></tr><tr><td><p>2017/18</p></td><td><p>M5
Junctions 4A-6</p></td><td><p>8.8</p></td><td><p>133.30</p></td></tr><tr><td><p>2018/19</p></td><td><p>M60
Junction 8 to M62 Junction 20: Smart Motorway</p></td><td><p>12.4</p></td><td><p>297.00</p></td></tr><tr><td><p>2018/19</p></td><td><p>M6
Junctions 16-19</p></td><td><p>18.2</p></td><td><p>265.00</p></td></tr><tr><td><p>2018/19</p></td><td><p>M1
Junctions 23a-25</p></td><td><p>6.7</p></td><td><p>139.60</p></td></tr></tbody></table><p><strong>
</strong></p><p> </p>
|
|