question text To ask the Secretary of State for Transport, pursuant to the Answer of 10 September 2015 to Question 9153, whether he received advice from officials in his Department on the potential deferral of Network Rail projects prior to 15 June 2015. more like this
tabling member constituency Nottingham South more like this
tabling member printed
Lilian Greenwood more like this
uin 10084 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2015-09-16more like thismore than 2015-09-16
answer text <p>As the Secretary of State told the Transport Select Committee in July 2015, he received advice in September 2014 that there was a cost overrun of some £2 billion for Network Rail enhancement projects. This advice identified measures to bring costs back down. It did not advise pausing Midland Main Line electrification or Transpennine electrification.</p><p> </p><p>15<sup>th</sup> June 2015 was the first day on which that the Secretary of State received advice that these two projects should be paused.</p><p> </p> more like this
answering member constituency Devizes more like this
answering member printed Claire Perry more like this
question first answered
less than 2015-09-16T15:34:29.61Zmore like thismore than 2015-09-16T15:34:29.61Z
answering member
3974
label Biography information for Claire Perry more like this
tabling member
4029
label Biography information for Lilian Greenwood more like this